Step 16: Remedial Works Plan Submission

Portal Status: Plan Submitted
Submit remedial works plan and supporting documents via portal.
Required Documents: Plan, supporting documentation, updated quotes.
Tips: Keep screenshots of portal submissions.

Step 17: Commencement Notices

Portal Status: Pre-Commencement
Submit notices to DCB Scheme (7–14 days before start) and Building Control (14–28 days).
Required Documents: Copies of both notices.
Links: Building Control – Donegal County Council

Step 18: Time Limits Awareness

Portal Status: Timeframe Awareness
Complete works within 130 weeks (~2½ years). Submit final grant claim within 65 weeks of starting works.
Tips: Track deadlines with calendar or portal reminders.

Step 19: Approval to Start Works

Portal Status: Approved to Commence
Receive formal grant approval and confirm start date.
Required Documents: Approval notice from portal.

Step 20: If Issues Arise Later

Portal Status: Further Information Request
Council may request further information or clarifications.
Tips: Respond promptly; keep copies of all correspondence.

Step 21: Keeping Records

Portal Status: Works Underway
Keep all invoices, receipts, photos, and logs of site findings.

Step 22: Payment Claims

Portal Status: Inspection Stage
Attend inspections; note corrections if required.