This timeline provides a detailed overview of defective concrete in Ireland, combining scientific research, government action, and homeowner experiences. All references are included for verification.
Phase 1
Prepare your application
Phase 2
Preparing for the build
Phase 3
Rebuilding your home
Phase 4
Final Steps

Step 16: Remedial Works Plan Submission
Portal Status: Plan Submitted
Submit remedial works plan and supporting documents via portal.
Required Documents: Plan, supporting documentation, updated quotes.
Tips: Keep screenshots of portal submissions.
Step 17: Commencement Notices
Portal Status: Pre-Commencement
Submit notices to DCB Scheme (7–14 days before start) and Building Control (14–28 days).
Required Documents: Copies of both notices.
Links: Building Control – Donegal County Council
Step 18: Time Limits Awareness
Portal Status: Timeframe Awareness
Complete works within 130 weeks (~2½ years). Submit final grant claim within 65 weeks of starting works.
Tips: Track deadlines with calendar or portal reminders.
Step 19: Approval to Start Works
Portal Status: Approved to Commence
Receive formal grant approval and confirm start date.
Required Documents: Approval notice from portal.
Step 20: If Issues Arise Later
Portal Status: Further Information Request
Council may request further information or clarifications.
Tips: Respond promptly; keep copies of all correspondence.
Step 21: Keeping Records
Portal Status: Works Underway
Keep all invoices, receipts, photos, and logs of site findings.
Step 22: Payment Claims
Portal Status: Inspection Stage
Attend inspections; note corrections if required.