Phase 1
Prepare your application
Phase 2
Preparing for the build
Phase 3
Rebuilding your home
Phase 4
Final Steps

Step 8: Approval to Proceed
Portal Status: Decision Accepted
Accept remediation option and grant. Planning and preparatory work can begin (do not start building work yet).
Required Documents: Acceptance confirmation in portal.
Tips: Keep screenshots and emails.
Step 9: Preparation Stage
Portal Status: Preparation Stage
Prepare plans, quotes, energy checks. Wait for portal prompt before commencing works.
Required Documents:
Draft remedial works plan
Preliminary quotes
Tips: Organize all documents in one folder.
Step 10: Confirm Building Professional
Portal Status: Professional Confirmation Required
Confirm registered architect, engineer, or surveyor to prepare remedial works plan.
Required Documents: Professional registration confirmation.
Tips: Check experience with defective concrete blocks.
Step 11: Remedial Works Plan
Portal Status: Plan Preparation
Professional prepares plan showing scope and sequence of work.
Required Documents: Draft remedial works plan.
Tips: Keep copies for reference and cost tracking.
Step 12: Planning Permission Check
Portal Status: Planning Assessment
Confirm whether planning permission is required for your home.
Required Documents: Planning permission application (if required).
Links: Planning – Donegal County Council
Step 13: BER / Energy Assessment
Portal Status: BER / Energy Assessment
Energy assessment may be required for building control compliance.
Required Documents: BER certificate if needed.
Links: SEAI BER Guide
Tips: Only schedule assessment when instructed.
Step 14: SEAI Grants (Optional)
Portal Status: Energy Grants Considered
You may be eligible for SEAI energy grants.
Required Documents: Registration with SEAI if pursuing grants.
Links: SEAI Grants
Step 15: Quotes & Cost Planning
Portal Status: Costing in Progress
Collect contractor quotes and review costs/timeline.
Required Documents: Written quotes from contractors.
Tips: Keep copies for submission and comparison.